yes. Multiple designs may be included in one design.
5 months
no
3 months
Reinstatement of priority is accepted on the grounds of "due care".
Examination of form only. The utility model application is examined for compliance with formal requirements, uniformity and registrability. If there is no special requirement, no novelty review will be conducted. The applicant can submit a request for delay in grant within 2 months from the filing date/priority date, and the grant can be delayed for 15 months at the latest.
Reinstatement of priority is accepted on the grounds of "due care".
no
yes
yes
- via Paris Convention : 12 months from earliest priority date.
- via Nationalization of PCT : 31 months from earliest priority date.
- Validation of European Patent in EPO member states: 3 months from the date of European patent grant